What a roof replacement costs and why bids spread so widely
Roof bids are driven by area, pitch, layers to tear off and what the decking looks like underneath, and none of that shows in an online average. What public data does show: the median roofer earns $26.65 an hour, asphalt roofing producer prices are 47.5% higher than in January 2020, and a re-roof permit can be a flat $66.00 (Grand Rapids) or a fee scaled to the value of the job (Reno, Portland).
Roofers price by the square, not the hour
A "square" is 100 square feet of roof surface, and nearly every bid is built from squares times a rate, then adjusted. Nobody will quote you hours. That does not mean hours do not matter; the rate per square is hours in disguise, and the adjustments tell you where the hours are.
Pitch. Past a certain steepness the crew cannot walk the roof. They work from roof jacks and harnesses, everything moves slower, and the rate climbs.
Height and access. Two stories, no driveway for the dumpster, landscaping that has to be protected.
Tear-off. One layer or several. Disposal is charged by weight.
Cut-up. Valleys, dormers, skylights, chimneys and walls all need flashing, and flashing is slow, skilled work. A simple gable goes fast. A roof with many planes does not.
Decking. Nobody knows what the sheathing looks like until the old roof is off. A good bid gives a unit price for replacing sheets so there is no argument on tear-off day.
The safety line is not optional
Federal rules require fall protection for each employee engaged in residential construction activities 6 feet or more above lower levels: guardrails, safety nets or personal fall arrest. A crew that sets anchors and ties off is slower than one that does not, and the legitimate bid carries that time. If one number is far below the rest, look at how that crew works on a roof before you look at anything else.
The labor arithmetic
| National wage point | Wage / hr | Loaded / hr | Implied billed hr, 15.5% margin | Implied billed hr, 29.9% margin | One worker-day (8 hr) at 29.9% |
|---|---|---|---|---|---|
| 25th percentile | $22.24 | $31.99 | $37.84 | $45.64 | $365 |
| Median | $26.65 | $38.33 | $45.34 | $54.68 | $437 |
| 75th percentile | $31.44 | $45.22 | $53.49 | $64.51 | $516 |
See roofer wages for every metro.
| National wage point | Wage / hr | Loaded / hr | Implied billed hr, 15.5% margin | Implied billed hr, 29.9% margin | One worker-day (8 hr) at 29.9% |
|---|---|---|---|---|---|
| 25th percentile | $23.32 | $33.54 | $39.68 | $47.85 | $383 |
| Median | $29.12 | $41.89 | $49.55 | $59.75 | $478 |
| 75th percentile | $36.94 | $53.14 | $62.85 | $75.80 | $606 |
See carpenter wages for every metro.
Roofing is weather work. The annual wage BLS publishes assumes 2,080 hours, which a roofer in a snow state will not get, so the hourly figures are the honest ones. Roofing also carries heavy workers compensation premiums compared with most trades, which means the national burden ratio in the table probably understates a roofing firm's real loading. Decking repairs are carpentry, so that wage is shown too.
Materials
| Series | BLS series ID | Month | Index | 12 months | Since Jan 2020 |
|---|---|---|---|---|---|
| Prepared asphalt and tar roofing and siding products | WPU1361 | October 2026 (p) | 365.9 | +2.3% | +47.5% |
| Plywood | WPU083 | October 2026 (p) | 312.4 | +16.9% | +60.4% |
| CPI-U, all items, U.S. city average | CUUR0000SA0 | September 2026 | 336.9 | +3.7% | +30.6% |
Permits
Not every city requires a permit for a like-for-like re-roof, and those that do charge in different ways.
| City | Line on the schedule | Fee | Schedule |
|---|---|---|---|
| Grand Rapids, MI | Residential re-roofing, flat fee, 2 inspections included | $66.00 | Planning, Design and Development Fee Schedule, FY 2027, effective July 1, 2026 |
| Reno, NV | Residential EZ permit: reroof | By valuation, from the city's permit fee table | EZ Permits and Miscellaneous Fees, effective July 1, 2026 |
| Portland, OR | Building permit, work valued $2,001 to $25,000: fee for the first $2,000 | $220.85 | Building and Other Permits Fee Schedule, effective July 10, 2026 |
| Portland, OR | Building permit, each additional $1,000 of value up to $25,000 | $13.91 | Building and Other Permits Fee Schedule, effective July 10, 2026 |
Under a valuation schedule the fee follows the contract price. On Portland's table a job valued between $2,001 and $25,000 pays $220.85 for the first $2,000 plus $13.91 for each additional $1,000.
Comparing roof bids
Put them in a grid: squares measured, layers removed, underlayment type, shingle line, flashing replaced or reused, ventilation changes, decking unit price, permit, cleanup, warranty on labor. Bids that differ in total almost always differ somewhere in that grid. And follow the FTC's line on payment: do not pay the full amount up front, and never make the final payment until the work is done.
Why did one roofer measure more squares than another?
Different waste factors and different treatment of hips, valleys and starter courses. Ask each for the measured roof area before waste. If those match, the difference is allowance; if they do not, one of them measured wrong.
Is a re-roof permit expensive?
It depends on the method. Grand Rapids charges a flat $66.00 with two inspections included. Cities that charge by valuation scale the fee with your contract price, so a bigger roof pays more.
Related guides
Sources
- BLS Occupational Employment and Wage Statistics, May 2025 metropolitan, state and national files
- BLS Employer Costs for Employee Compensation, June 2026, Table 4 (private industry by occupational and industry group)
- NAHB Eye on Housing, Remodelers Saw Profit Margin Gains in 2024 (Remodelers' Cost of Doing Business Study)
- Aswath Damodaran, NYU Stern, Margins by Sector (US), data as of January 2026
- BLS Producer Price Index commodity data and CPI-U, retrieved through the BLS public data API
- Grand Rapids, MI: Planning, Design and Development Fee Schedule, FY 2027, effective July 1, 2026
- Reno, NV: EZ Permits and Miscellaneous Fees, effective July 1, 2026
- Portland, OR: Building and Other Permits Fee Schedule, effective July 10, 2026
- each employee engaged in residential construction activities 6 feet or more above lower levels