- Home
- Job guides
- Whole-house rewire
Job guide / electrician, drywall installer
Rewiring a house: the cost is in the walls
Rewiring an occupied, finished house is one of the most labor-heavy electrical jobs there is, because the wire is cheap and the route to pull it is not. Portland permits it by floor area: $408.00 for the first 1,000 square feet, service included, and $93.00 per additional 500. Electricians earn a national median of $30.38 an hour, about $499 per implied worker-day at a remodeler's margin.
Open walls or closed walls
That is the question that decides everything. In a gutted house an electrician drills studs and pulls cable through open framing at speed. In a finished house every run is fished: down from the attic or up from the basement, through holes cut at the top and bottom of each wall cavity, around fire blocks nobody knew were there. The same circuit takes several times the labor.
If you are planning other work that opens walls, such as a kitchen or a repipe, rewire then. The saving is larger than any negotiating you can do on rate.
What a full rewire includes
- New branch circuits to every room, laid out to current code, which usually means more circuits than the house had.
- New boxes, devices and cover plates throughout.
- Hardwired, interconnected smoke alarms where the code requires them on a rewire.
- Often a new panel and service, since old wiring and an old service tend to travel together. See the panel upgrade guide.
- Removal or abandonment of the old wiring. Dead knob-and-tube left in place is normal; live knob-and-tube left in place is not a rewire.
What it often does not include: patching and painting the access holes. As with a repipe, find out who closes the walls.
Estimating the labor
Electricians bid rewires from a count: rooms, openings (each outlet, switch and light is one), stories, and whether there is an attic and basement to work from. Lath and plaster is slower than drywall. Finished basements and flat roofs take away the easy routes.
| National wage point | Wage / hr | Loaded / hr | Implied billed hr, 15.5% margin | Implied billed hr, 29.9% margin | One worker-day (8 hr) at 29.9% |
|---|---|---|---|---|---|
| 25th percentile | $23.76 | $34.18 | $40.43 | $48.75 | $390 |
| Median | $30.38 | $43.70 | $51.69 | $62.34 | $499 |
| 75th percentile | $40.36 | $58.05 | $68.67 | $82.82 | $663 |
See electrician wages for every metro.
| National wage point | Wage / hr | Loaded / hr | Implied billed hr, 15.5% margin | Implied billed hr, 29.9% margin | One worker-day (8 hr) at 29.9% |
|---|---|---|---|---|---|
| 25th percentile | $22.81 | $32.81 | $38.81 | $46.80 | $374 |
| Median | $28.33 | $40.75 | $48.20 | $58.13 | $465 |
| 75th percentile | $35.69 | $51.34 | $60.73 | $73.23 | $586 |
See drywall installer wages for every metro.
Ask each bidder for crew size and duration and multiply. This is a job where the worker-days are large enough that the 25th and 75th percentile rows are far apart in dollars. Who is on the crew matters.
Permit lines
| City | Line on the schedule | Fee | Schedule |
|---|---|---|---|
| Portland, OR | Residential wiring package, new and remodels, 1,000 square feet or less, service included | $408.00 | Electrical Permit Fee Schedule, effective July 10, 2026 |
| Portland, OR | Wiring package, each additional 500 square feet or portion | $93.00 | Electrical Permit Fee Schedule, effective July 10, 2026 |
| Grand Rapids, MI | Electrical permit application, includes 1 inspection | $52.00 | Planning, Design and Development Fee Schedule, FY 2027, effective July 1, 2026 |
| Grand Rapids, MI | Electrical: general branch circuit | $10.00 | Planning, Design and Development Fee Schedule, FY 2027, effective July 1, 2026 |
| Grand Rapids, MI | Electrical: up to 200 amp service | $17.00 | Planning, Design and Development Fee Schedule, FY 2027, effective July 1, 2026 |
Portland's wiring package fee is the clearest published example of how cities scale a rewire permit to house size. Grand Rapids builds the fee from an application plus per-circuit and service items.
Copper and devices
| Series | BLS series ID | Month | Index | 12 months | Since Jan 2020 |
|---|---|---|---|---|---|
| Copper wire and cable | WPU10260314 | October 2026 (p) | 610.0 | +25.5% | +101.9% |
| Wiring devices | WPU1171 | October 2026 (p) | 397.6 | +4.8% | +66.1% |
| CPI-U, all items, U.S. city average | CUUR0000SA0 | September 2026 | 336.9 | +3.7% | +30.6% |
Comparing bids
Get the opening count on each bid. Confirm arc-fault and ground-fault protection are included where required, that the smoke alarms are in, that the panel scope is stated, and that there is a price per additional opening for the things you will think of later. Ask how they protect floors and how many holes to expect per room.
Is copper the reason rewires are expensive?
No. Copper wire and cable is 101.9% higher at the producer level than in January 2020, but cable is still a minor share next to many worker-days of electrician labor at a loaded cost near $43.70 an hour.
How is a rewire permit priced?
Portland uses a wiring package by floor area: $408.00 for 1,000 square feet or less including the service, then $93.00 for each further 500 square feet or part.
Related guides
- Bathroom remodel
- Central air conditioner replacement
- Drywall hanging and finishing
- EV charger installation
- Electrical panel upgrade
- Heat pump water heater installation
Sources
- BLS Occupational Employment and Wage Statistics, May 2025 metropolitan, state and national files
- BLS Employer Costs for Employee Compensation, June 2026, Table 4 (private industry by occupational and industry group)
- NAHB Eye on Housing, Remodelers Saw Profit Margin Gains in 2024 (Remodelers' Cost of Doing Business Study)
- Aswath Damodaran, NYU Stern, Margins by Sector (US), data as of January 2026
- BLS Producer Price Index commodity data and CPI-U, retrieved through the BLS public data API
- Portland, OR: Electrical Permit Fee Schedule, effective July 10, 2026
- Grand Rapids, MI: Planning, Design and Development Fee Schedule, FY 2027, effective July 1, 2026